2017 Asphalt Work

asphalt2015-complete

The buildings, carpentry, and balcony work will consume much of the association’s budget for the year, however, the board will be able to replace 33 of the smaller driveways including curb cutting.  With 63 driveways already replaced, this will bring our total to 96 (38%).

Potholes will be filled as soon as the asphalt plants come online (end of April / early May).  The newly renovated driveway between 8108/8808 will be sealcoated.

The board is also working to establish a 2-4 year plant for more extensive asphalt renovation and drainage improvements.

Pothole Repair

pothole_slider

The board of directors has proposals for pothole repair, so we appreciate your patience as we know there numerous areas in need of repair.

While the remainder of the buildings are seeing wood repair and painting, in 2018 the board expects to make asphalt repair an even greater budget priority.

Again, thank you for your patience while we wait for asphalt plants to begin to come online for the season.

Driveway Replacement 2016

driveway

The board of directors has evaluated the asphalt condition throughout the association.  The asphalt in the worst condition was identified to be between 8108 and 8808.  The driveway area will be replaced in the Spring/Summer of 2016 including complete excavation, pitch, and drainage.

Following permits, the existing asphalt will be excavated and new base installed.  It will remain this way for about a month and allowed to settle.  Following this, the new asphalt will be installed.

Drainage & Excavation To Begin May 5

asphalt

The Association will begin a drainage project on Tuesday May 5th. The construction crew will be installing new underground drain piping and connecting downspouts to the new system. The project will begin in the 8808-8814 area on Tuesday May 5th. This area should be completed by Thursday May 7th. If you live in this area we are asking that all cars be moved to alternate parking areas outside of the construction location between the hours of 7:30 am-4:30 pm from May 5th-May 7th.

The crew will be mobilizing on Monday May 4th, but excavation will begin on May 5th.

For any questions or concerns, please contact ACM at 630-320-1133 or customercare@acmweb.com