Drainage & Excavation To Begin May 5

asphalt

The Association will begin a drainage project on Tuesday May 5th. The construction crew will be installing new underground drain piping and connecting downspouts to the new system. The project will begin in the 8808-8814 area on Tuesday May 5th. This area should be completed by Thursday May 7th. If you live in this area we are asking that all cars be moved to alternate parking areas outside of the construction location between the hours of 7:30 am-4:30 pm from May 5th-May 7th.

The crew will be mobilizing on Monday May 4th, but excavation will begin on May 5th.

For any questions or concerns, please contact ACM at 630-320-1133 or customercare@acmweb.com